Build a hügelkultur berm for a swale just in front of the front fence (east side) serving the big field — a wood-cored, water-holding, self-fertilizing mound that also uses up the property's excess wood. Captured from a voice note 260925 for desk review.

skills::
lead:: @Niko
start:: #y/2026/Fall
estimated completion:: #y/2027/Fall
season::


Project - Overview

Purpose

Turn the pile of excess wood into a productive earthwork: a hügelkultur mound built as the berm of a swale on the east side of the front fence, catching and holding water for the big field while the buried wood slowly breaks down into a fertile, moisture-retentive planting bed.

Objectives

Background Info

Horizon: start this fall 2026 and carry it through for ~a year+ — a long-running, phased build (one 10-ft section at a time as wood and labor allow), not a single work-day.

Hügelkultur buries logs/branches under a soil mound; the rotting wood acts as a sponge (holds water, releases it slowly) and a slow-release nutrient bank, so the bed needs less irrigation over time — a good fit for a low-water Reno site and for consuming a wood surplus. Pairing it with a swale berm doubles it as a water-harvesting earthwork.


Project - Details

Open Decisions

# Decision Options Status
D-1 How gravity water reaches the west half (a) open ditch or furrow: ~0.1–0.3% fall (5–14 in over 400 ft); steeper erodes clay. (b) pipe feeding gravity drip: the pipe's slope barely matters; what counts is total height (head) above the emitters, ~2.5–5 ft for low-pressure drip. Open — needs the survey
D-2 Where the west half's water comes from The ditch, a pond, or a tank. Its height sets the head available for D-1. Open
D-3 Berm depth 2 / 3 / 4 ft (see Questions) Open

Design

Grade along the fence (captured 260925, not yet surveyed)

The front fence is roughly 400 ft, and the two halves need opposite grades:

First step: survey what fall the 400 ft already has. That sets what's possible for both halves.

Scope

In: the swale + hügelkultur berm on the east front-fence line for the big field, built in 10-ft sections.
Out: what gets planted on the berm (decide once it's built), and the rest of the big-field earthworks.

Milestones

A - Survey + mark (fall 2026)

Measure the fall along the fence and stake the level swale line. This refines the plan. The survey settles D-1 (ditch or pipe), D-2 (water source), and D-3 (depth), and confirms where the east half ends and the west half starts. Nothing gets dug before this.

B - Pilot section

Build the first 10-ft section and review it before continuing.

C - Phased build (through fall 2027)

Continue one 10-ft section at a time as wood and labor allow.

Tasks


Project - Resources

Budget

Materials & Tools

Equipment

References / Examples


Documentation and Media

Photos and Videos

Before/after per 10-ft section.

Documents

Technologies

Questions / Unknowns


Collaboration and Participation

How to Get Involved

A good work-day build — hauling wood, digging, capping. Contact @Niko.